What Property Managers Get Wrong About Build to Rent EICR Compliance
Managing EICR compliance across a Build to Rent development should be straightforward. Every apartment needs an Electrical Installation Condition Report. Every report expires. Every expiry needs tracking. Yet in practice, BTR operators across Manchester consistently fall into the same traps — traps that cost money, create compliance gaps and frustrate residents.
After completing EICR programmes across 18 developments and 874+ apartments in Greater Manchester, we have seen every mistake in the book. This article covers the five most common ones and explains how to avoid each.
Mistake 1: Treating Each Apartment as a Separate Job
This is the most expensive mistake and the most common. A BTR operator contacts three or four local electricians, gets individual quotes per apartment, and sends different contractors to different floors on different days. The result is chaos.
Each contractor has their own scheduling process, their own access requirements, their own reporting format and their own remedial pricing. The building manager spends hours coordinating access, chasing certificates, reconciling invoices and dealing with residents who have been visited multiple times by different people.
The cost: A 200-apartment development managed this way typically takes 6 to 12 months to complete, generates 200 separate invoices, produces certificates in multiple formats, and creates an administrative burden that consumes 2 to 3 hours per week of management time.
The fix: Treat the entire development as one coordinated programme. A single contractor working to a pre-planned schedule, with agreed pricing, consistent reporting and one point of contact. At Manchester Compliance, our two-electrician teams complete up to 8 apartment EICRs per day, working systematically through each floor. A 200-apartment block is completed in approximately 5 weeks, not 12 months.
Mistake 2: Relying on Resident Access
The traditional approach to apartment EICR testing requires the resident to be home. An appointment is booked. The electrician arrives. The resident is out, or forgot, or did not get the letter. The electrician leaves. A new appointment is booked. The cycle repeats.
In conventional EICR programmes, no-access rates of 15 to 30 per cent are normal. For a 200-apartment development, that means 30 to 60 apartments require rescheduling — adding weeks to the programme, frustrating the electrician and increasing costs through wasted visits.
The cost: Every failed access visit costs the operator. The electrician charges a call-out fee or absorbs it into higher per-unit pricing. The management team spends time rebooking. The programme timeline extends. And until every apartment is tested, the development is not fully compliant.
The fix: Management key access. In every BTR development we work in, we collect master keys from the building management team at the start of each day. Our engineers access each apartment using the management key, complete the EICR, and return the keys at the end of the day. Residents are notified in advance but do not need to be home. Our no-access rate across all developments is 0 per cent.
This is not an unusual arrangement. BTR leases typically include access clauses for maintenance and compliance. The management company has the right — and the obligation — to ensure electrical testing is completed. Using management keys is the most efficient way to exercise that right.
Mistake 3: Waiting Until Certificates Expire
Reactive compliance means waiting until EICR certificates are about to expire, then scrambling to book testing. In a BTR development where apartments were let at different times, certificates expire on different dates throughout the year. The result is a constant drip of individual bookings, each requiring separate coordination.
Worse, some certificates slip through. A busy management team misses an expiry date. The apartment is now non-compliant. If an electrical incident occurs in that period, the operator faces serious liability — the Electrical Safety Standards in the Private Rented Sector (England) Regulations 2020 require a valid EICR to be in place at all times during a tenancy.
The cost: Reactive testing costs more per unit (no volume efficiency), takes longer (individual scheduling), creates compliance gaps (missed expiries) and generates more administration (tracking dozens of different expiry dates).
The fix: Consolidate all testing into one annual or biannual programme. When we take on a BTR development, we align all EICR expiry dates across the building. If certificates expire at different times, we bring forward the earliest expiries and test everything in one block. From that point on, the entire development is on a single testing cycle. One programme, one schedule, one set of certificates, one expiry date.
Mistake 4: Separating EICR Testing from Remedial Work
A common procurement approach is to hire one contractor for EICR testing and a different contractor for any remedial work that arises. The logic seems sound — get an independent test, then get quotes for repairs. In practice, it doubles the disruption and delays compliance.
When testing and remedials are separated, the process looks like this: the EICR contractor identifies a fault, writes it up, sends the report to the management company. The management company reviews the report, contacts a remedial contractor, gets a quote, approves the quote, schedules the work. The remedial contractor visits the apartment (requiring a second access visit), completes the repair, and the original EICR contractor returns for a re-test (a third visit). Total: three visits to the apartment, weeks of delay, and the apartment is non-compliant throughout.
The cost: Three access visits per apartment with remedial needs. Weeks of delay between fault identification and resolution. Higher combined cost from two contractors. Administrative overhead managing two suppliers. Extended period of non-compliance.
The fix: Same-day remedials. Our electricians are qualified to both test and repair. When an EICR identifies a fault, the remedial team fixes it the same day. The apartment goes from tested to compliant in one visit. We use Schedule of Rates (SOR) pricing, which means every potential remedial item has a pre-agreed cost. The building manager does not need to wait for quotes — they can approve works instantly using the SOR schedule.
Mistake 5: Accepting Paper Certificates and Manual Tracking
Paper EICR certificates in a filing cabinet. Excel spreadsheets tracking expiry dates. PDF certificates emailed one at a time and saved into folder structures. This is how most BTR operators manage compliance documentation, and it is slow, error-prone and impossible to audit efficiently.
When a managing agent, insurer or local authority requests proof of compliance, the management team has to locate individual certificates, check they are current, compile them into a report and send them across. For a 200-apartment development, this can take a full working day.
The cost: Hours of management time for each compliance audit. Risk of misfiled or lost certificates. No real-time visibility of compliance status. Difficulty demonstrating compliance to stakeholders quickly.
The fix: Digital compliance management. All our EICR certificates are uploaded to the Eworks job management system on the day of testing. Building managers can access every certificate, every test result and every remedial record digitally, in real time. When an insurer or managing agent requests proof of compliance, it takes minutes, not hours.
The system also provides automatic tracking of expiry dates, so no certificate slips through. The building manager receives advance notification when the next testing programme is due, with a proposed schedule already drafted.
The Compound Effect
These five mistakes do not exist in isolation. They compound. A property manager treating each apartment as a separate job is also likely relying on resident access, which means higher no-access rates, which means longer programmes, which means more certificates expiring before the programme completes, which means more reactive testing.
Fixing one mistake helps. Fixing all five transforms BTR compliance from a constant administrative burden into a once-a-year programme that runs itself.
How Manchester Compliance Solves All Five
Our Build to Rent EICR programme is specifically designed to eliminate every one of these mistakes:
- One coordinated programme — not individual apartment bookings
- Management key access — 0% no-access rate across all developments
- Aligned expiry dates — one testing cycle for the entire building
- Same-day remedials — testing and repairs in one visit, SOR pricing
- Digital certificates — uploaded to Eworks the same day, accessible instantly
Discuss your Build to Rent EICR programme. Call 0161 706 1360 or email Info@manchestercompliance.co.uk.
View our Build to Rent services | Block management electrical compliance | How to plan a full-building compliance programme